A bill of quantities (BOQ) for a house is a measured list of what goes into it, sectioned by trade and written in the unit each trade buys in. It is not a price. This page builds one for a single-storey new home, in build order. It also names the line inside each section that most often goes missing.
A BOQ section is one trade's block of the document. A trade package is what that block becomes when a subcontractor prices it.
Key Takeaways
- A house BOQ is measured, not priced. Pricing applies rates to the same quantities, and the two should fail independently.
- Sections follow the build, because each is bought by a different trade.
- One unit per line, and the unit belongs to the trade. Cubic metres for concrete, lineal metres for edge beams, counts for doors.
- The omissions are predictable. Spoil, internal thickened beams, opening trims, roof pitch, cladding corners, wet-area set-downs.
- Most new homes never get one. Builders usually price from drawings and a specification, not a standard-method BOQ.
Before the Trades: The Measurement Set
You cannot measure a trade from the wrong sheet. Concrete comes off the structural drawings, cladding off the elevations, and counts off the schedules rather than the plan.
A usable set is smaller than it sounds. It runs to plans, elevations and details; structural drawings; the door, window, wall and lintel schedules; the specification; and the site survey. It also needs the soil class, which sets the slab class.
The first check is the footprint. The architectural plan and the structural slab layout should agree on the outside of the building. If they do not, every quantity below the slab inherits the error. Scaleline's slab and footings take-off guide makes the same point. Read the structural drawing, because that sheet governs what is poured.
Scaleline is a DDDI Group company, and DDDI Group publishes this article. Links to Scaleline are related-party referrals, not independent recommendations. Scaleline measures new homes from drawings and does not price them; it is not an AIQS-certified quantity surveying practice.
The Eight Sections, in Build Order
A house BOQ is written in the sequence the work happens. That is the sequence each package gets let. Each section uses a narrow unit set, and the same line goes missing every time.
| Section | Units used | Line most often missed |
|---|---|---|
| Site works and earthworks | m² strip, m³ cut and fill, lm sediment control | Spoil disposal and over-dig |
| Slab and footings | m² slab area, lm edge beams, m³ concrete, each piers | Internal thickened beams |
| Frame | lm plates and bracing, each studs and lintels | Studs at corners and trimmers at openings |
| Roof | m² true sloped area, lm battens and fascia, each downpipes | Pitch applied per face rather than once |
| Cladding | m² net wall area, lm corners and flashing | Corner stop-ends and control joints |
| Windows and doors | each, by schedule type | Count taken from the plan instead |
| Linings | m² board and paint, lm cornice and skirting | Ceiling height driving wall area |
| Wet areas and finishes | m² waterproofing, screed and tiling, each fixtures | Set-downs and screed depth |
Site Works and Earthworks
This section has the least drawing behind it. That is why it is the one most often under-measured. Plans show finished levels, not the excavation needed to reach them.
Measure strip and clear in square metres, cut and fill in cubic metres, sediment control in lineal metres. Then add the lines no drawing shows: over-dig below the slab, spoil disposal, rock, service trenching, temporary fencing and the footpath crossing. VIABUILD puts it plainly. Drawings show finished work, not excavation over-dig, temporary propping or the connection the authority will need (VIABUILD).
If the soil report is not in hand, the section is an allowance. Say so on the line.
Slab and Footings
Two unit families carry this section, and mixing them is the usual error. Slab area is square metres. Edge beams and strip footings are lineal metres, concrete is cubic metres, and pods and piers are counts.
Measure slab area to the outside of the slab edge, not the brickwork. Give each separately poured zone its own line, so a step-down or an alfresco can be priced on its own. Edge beams run the perimeter. Internal thickened beams run under load-bearing walls. They are the line a hand take-off most often loses, because they do not sit on the outside edge. Termite protection is its own set of lines. A published builders BOQ sample prices perimeter treatment by lineal metre. Penetration protection is priced as a job and pier protection as a count (AVL Estimating sample).
Consider a simple rectangular slab. Its concrete volume builds up as follows. The figures are illustrative, not a real job.
Main slab 12.0 m x 8.0 m = 96.0 m2 at 0.10 m = 9.60 m3
Edge beam 0.30 m x 0.40 m over 40.0 lm = 4.80 m3
Deduct overlap beam top inside the slab already
counted: 40.0 lm x 0.30 m x 0.10 m = -1.20 m3
Net concrete = 13.20 m3
The overlap deduction is the step most hand take-offs skip. Without it the beam is counted twice where it passes under the slab. The order then comes up short. The method is in Scaleline's slab and footings take-off guide.
Frame and Roof
Frame
Plates are length, studs are a count, and every opening changes the count in three places. Measure wall length in lineal metres off the floor plan, wall by wall, so each line can be checked. Plates are wall length times two. Studs come from the schedule spacing, over the net wall length after openings.
The three places an opening changes the count are the lintel, the trimming studs either side, and the sill trimmer below a window. Add the studs at corners and intersections. A per-metre count does not produce those. Scaleline's wall framing take-off guide has the method.
Roof
Plan area is not roof area. A roof plan is drawn flat and the sheet is fixed to a slope. So every face is converted using its own pitch.
For a roof rising 6 units over a run of 12, the factor is √(1 + (6 ÷ 12)²), or 1.118. A 100 m² plan face is 111.8 m² of sheet. Treating a two-pitch roof as one pitch is the most common roof quantity error. It is invisible until the sheets arrive short.
Once the area is right, the rest is linear and counted. Battens, fascia, gutter, ridge, hips and valleys run in lineal metres, while downpipes and flashings are counts. Flashings at penetrations are additions, not deductions. Scaleline's roof take-off guide covers each face.
Cladding, Windows and Doors
Net area is the quantity. The non-area items are where the money goes.
Read the elevations rather than the floor plan. Elevations give true heights, including any raised floor or parapet. Gross wall area is length times height. Deduct openings at their structural opening size, read off the schedule.
Elevation 15.0 m x 2.7 m = 40.50 m2 gross
Deduct window 1.8 m x 1.2 m = -2.16 m2
Deduct door 0.9 m x 2.1 m = -1.89 m2
Net wall area = 36.45 m2
What stays in the gross figure is a convention decision. Under the general rules of the Australian Standard Method of Measurement, no deduction is made from area-measured items for voids under 1 m². The same rule applies to volume-measured items under 0.1 m³ (ASMM 6th edition).
The non-area items are the ones a quick take-off skips: corner stop-ends, control and jointing, and base and head flashings. Scaleline's Hebel external wall take-off guide names those three as the reason a cladding quantity looks lean until the invoices arrive.
Windows and doors are a count from the schedule, not the plan. The schedule settles how many the deduction should have removed.
Linings, Wet Areas and Finishes
Plasterboard is measured in square metres of wall and ceiling. The wall figure is driven by ceiling height. That is why 2.7 m ceilings are not a small change to a lining amount. Cornice and skirting are lineal metres. Paint follows the areas it covers, plus ceilings. Wet areas add waterproofing, screed and tiling, all in square metres.
The omissions here are about extent rather than arithmetic. Wall tile extent is the clearest case. Full height, half height and skirting only produce very different quantities, and none of them is drawn. Houzz's list of items missing from residential drawings includes wall tile extent, joinery without drawings, and lighting and flooring specification (Houzz AU, 10 July 2015). An Australian BOQ audit guide adds wet-area set-downs and screeds (Estiflow). Joinery is an allowance unless there are joinery drawings.
Preliminaries, Allowances and the Standard Question
Anything that cannot be measured from the documents is an allowance. It only works if labelled as one. Preliminaries cover what the job needs regardless of trade: scaffolding, crane, site facilities, temporary services, insurance, authority fees and supervision. Allowances cover work that is genuinely unresolved: joinery without drawings, landscaping without a plan, rock without a geotechnical report.
The rule that makes the document usable is separation. Measured scope stays measured. An allowance stays an allowance and carries its basis. Estiflow's residential BOQ guide is direct about why. Mixing the two categories is where tender risk starts to hide (Estiflow).
The reference standard is ANZSMM, published by AIQS with the New Zealand institute and both Master Builders associations. ANZSMM 2018 is based on the sixth edition of the Australian standard. It replaced NZS4202 in New Zealand (Registered Master Builders, 9 February 2018).
Most new-home BOQs in Australia are not prepared to ANZSMM. Builders more often price from drawings and a specification, with the estimate living in their own system. Where a house BOQ is prepared, it is usually a builder's trade-format document rather than a standard-method one (NEWIN). Without a shared rule, two builders' quantities are not directly comparable, even when both are accurate.
Frequently Asked Questions
What does BOQ mean in construction?
A bill of quantities: a measured list of the materials and work in a project, organised by trade and written in the unit each item is bought in. It records quantities, not prices, though a priced version is common on tenders. The pillar guide to bills of quantities covers the definition.
How much does a quantity surveyor charge per hour?
Practices price three ways: hourly, a percentage of construction cost, or a fixed fee per dwelling or per trade. Hourly suits variations and dispute support; fixed fees suit a defined scope. Ask which basis is quoted before comparing two numbers. Quantity take-off services sets out what a fixed-scope job should include.
What is the average cost per square metre to build a house in Australia?
For example, the AIQS Building Cost Index for September 2026 puts a standard residential house at roughly $1,600/m² in Canberra. The same index puts it at about $1,980/m² in Brisbane, excluding GST (MCG Quantity Surveyors, September 2026 edition). That is a benchmark, not a quote.
What is the most expensive part of building a house?
The trades carrying the largest measured scope are slab and footings, frame, and the roof and cladding package. Each is driven by a structural or elevation decision rather than a finish selection. That is why omissions there cost more than omissions in finishes.
Should a house BOQ be priced or unpriced?
Unpriced for comparison, because a shared quantity list lets several trades price the same scope. Priced for a contract or a variation schedule, because a rate against a quantity is what makes a variation calculable. See quantity take-off versus bill of quantities.
What the Exercise Proves
A house BOQ is a checklist executed in the right order with the right unit. The arithmetic is simple, which is why the document is checkable. Its value sits in what it forces you to notice.
The notice list is short. Spoil and over-dig. Internal thickened beams. Trims and lintels at every opening. Pitch per roof face. Corners and joints on the cladding. Set-downs in the wet areas.
If you want the finished article rather than the method, Scaleline publishes a sample report with a line-by-line worked example. You can also get started on your own set. For the column set and line rules, see bill of quantities format. For where the quantities come from, see construction takeoff software. For the numbers rolling into a feasibility, see property development costs.
Scaleline is a DDDI Group company, and DDDI Group publishes this article. Links to Scaleline are related-party referrals, not independent recommendations. Scaleline measures new homes from drawings and does not price them; it is not an AIQS-certified quantity surveying practice.
This guide is researched and edited by the DDDI Built Environment Research desk, which publishes industry research on property development and construction in Australia. It is fact-checked against primary sources before publication, and corrections can go to the research desk through the contact page. The editorial standard behind these articles is described on DDDI's about page.