A bill of quantities is a document that lists each measured item of work in a building project, trade by trade, with a description, a unit and a quantity against each line. It fixes scope; it does not fix price. In Australia the rules come from the Australian and New Zealand Standard Method of Measurement. Most new-home BOQs are not prepared to it.
Key Takeaways
- A BOQ is a scope document. Its purpose is to make several prices comparable, not to predict the final cost. If only one party is pricing, you may not need one.
- Trade order is what makes it usable. An elemental cost plan groups work by building element for planning; a BOQ groups work by trade so it can go straight to a subcontractor.
- Preparation is seven steps in a fixed order, and step one is checking the drawings. A BOQ measured off a superseded sheet is worse than no BOQ.
- The unit on each line is where bills fail. Mixing units inside a line passes any check on its totals, because the arithmetic stays consistent.
- Most detached houses are built without a BOQ. That is only a problem when more than one party has to price the same scope.
What a Bill of Quantities Is
A bill of quantities itemises the work. Each line carries a description of what is to be done, the unit it is measured in, and the quantity. The bill is measured from drawings and specifications, so it describes the building rather than a builder's opinion of it.
The standard literature gives it two jobs. Before contract, it breaks the works down so that tenderers price the same scope in the same structure. After contract, it gives a cost framework for valuing progress payments and variations (Davis and Baccarini, Curtin University). The meaning of the term is therefore narrower than most people assume: a bill is not a cost forecast.
It is also an old instrument, and its use has been contested for as long as it has existed. Bills of quantities have been in use in some form for over 300 years. A survey of 86 Australian building professionals, mostly consultant quantity surveyors, found that BQ preparation accounted for less than 25 per cent of their workload. The same survey found principals reluctant to make a BOQ part of the contract. It also found builders sceptical of a BOQ supplied for "information only", because it presents unreasonable risk. That was published in 2004, and the trend has not reversed since.
Three documents get confused with each other. A quantity take-off is the act of measuring. A BOQ is the organised, described result of that measurement. An estimate applies rates and allowances to quantities to produce a cost. Take-off, BOQ and estimate are three different documents, produced at different stages, and only one of them is meant to be priced by someone else.
A quantity take-off is the raw measurement before any description is applied, and an estimate is a bill of quantities with rates applied to it.
| Feature | Take-off | Bill of quantities | Estimate |
|---|---|---|---|
| Produces | Raw quantities | Described, itemised quantities | A cost |
| Stage | Any | Tender or procurement | Feasibility through tender |
| Priced? | No | Optionally | Yes |
| Prepared by | Estimator or take-off service | QS, estimator or take-off service | Estimator |
| Main use | Input to the next step | Comparing prices on one scope | Budgeting |
What a Bill of Quantities Contains
The section order is what makes a BOQ usable. It has to match the order in which a builder buys the work.
Each line carries an item code, a trade section, a description, a quantity and a unit. Where the bill is priced, it also carries a rate and an amount. The column set and line rules are worth getting right before the first line is written. A bill that cannot be checked line by line will not be trusted by the people pricing it.
For a detached house, the trade sections tend to run in build order:
| Section | Typical units |
|---|---|
| Preliminaries, site establishment, temporary works | item |
| Earthworks, excavation, disposal, backfill | m³ |
| Footings, slab, structural concrete | m³, m², lm |
| Frame, structural steel, trusses | lm, no., item |
| Roof covering, gutters, fascia, insulation | m², lm |
| External cladding, windows and external doors | m², no. |
| Internal linings, cornice, skirting | m², lm |
| Wet areas, waterproofing, tiling | m², no. |
| Joinery, cabinetry, benchtops, hardware | no., lm, item |
| Services: electrical, plumbing, drainage, HVAC | no., lm, item |
| External works, paving, landscaping, fencing | m², lm |
That order is deliberately not the same as the elemental order used in cost planning. An elemental cost plan groups work under headings like substructure, external walls and roof, following the AIQS Australian Cost Management Manuals. A BOQ is measured in trades, to the ANZSMM, and one element can contain several of them: external walls includes masonry, insulation and painting (Building Cost Planning, Open Educational Collective). Both groupings are correct for their purpose. They are not interchangeable.
The variant builders actually use is sometimes called a Builders BOQ. It is measured in trade format. Specifications, model numbers, code numbers and sizes sit in each trade line. The bill can then be sent to a subcontractor or supplier without a covering explanation (HSB Group). A trade-by-trade worked example for one house shows what that looks like filled in.
How a Bill of Quantities Is Prepared
Bill of quantities preparation runs in seven steps, in a fixed order. The order matters because each step depends on the one before. Knowing how to prepare a bill of quantities is therefore less about measuring skill than about not skipping ahead.
1. Assemble and verify the documents
Start with the drawing register, not the drawings. Confirm which revision of each sheet is current, that the specification matches the drawings, and that structural and services drawings have been issued rather than promised. A bill of quantities can only be as accurate as the drawings it is measured from. Incomplete drawings with performance-based specifications do not support a useful one (Cost Planner). The measurement period is not the period for finishing the design.
2. Fix the measurement rules before measuring
Decide what is measured, what is deducted, and to which standard. For a commercial tender that means the ANZSMM. For a house it is usually a stated house convention, and the only rule is that it is written down and applied consistently. Measuring first and reconciling later produces a bill with two conventions in it.
3. Take off the quantities
Work sheet by sheet, in metric, and group the measurements so they map onto the trade sections later. The discipline is traceability. Every quantity should tie back to a specific sheet and a location, so a challenge resolves by opening the drawing rather than redoing the work. Measuring PDF and DWG plans digitally covers the mechanics of doing this on screen.
4. Group into trade sections
This is the step that turns a pile of measurements into a bill. Keep the section order consistent between jobs, and keep the coding consistent so totals roll up in a way a reader can follow without asking.
5. Write the descriptions and assign units
A quantity on its own prices nothing. The description has to state the work, the material or specification, the location, and the unit. The unit is where bills fail quietly: mixing units within a single line survives every later check because the arithmetic stays internally consistent (ToolFoundry). Four units carry most of a house. Square metres cover areas such as wall linings and tiling. Cubic metres cover concrete and excavation. Lineal metres cover skirting, cornice and pipework. Number covers doors, windows and fixtures.
6. Check the bill before it is priced
Three checks, in this order. Cast the bill, so the parts add to the whole and the summary agrees with the sections. Check completeness against the drawing register rather than against your memory. Then read it as a subcontractor would, looking for the things that are always missing: sealants, trims, thresholds, temporary works, and anything the specification requires but no drawing shows. That last read-through is where most pricing disputes are prevented.
7. Issue with a revision and a query list
Issue the revision you measured, not the one that happened to be in the folder, and state it on the document. Send open questions as a query list rather than burying assumptions in a rate, so the person pricing can see what was decided and why. This is also the point where automated take-off is genuinely useful and where it is oversold. A tool can count symbols and detect areas on a clean vector set. The number that ends up in a contract still needs a person to approve it. That is the position the estimating firms actually running these tools take (The Good Builder, 22 October 2026).
If you are buying this as a service rather than doing it, what to check before you pay a take-off service covers the questions worth asking.
Who Prepares a Bill of Quantities in Australia
Three routes produce bills in Australia. Which one applies depends on the project type and who is paying for the bill. The client pays when the bill has to be independent of the bidders; the builder pays when it is an internal pricing tool.
A quantity surveyor. This is the traditional answer and still the standard on commercial tenders. Quantity surveyors determine, analyse and manage construction costs from feasibility through to occupancy, and measurement and BOQ preparation sit inside that (AIQS). They are usually engaged by the client, which is what makes the bill independent of any builder pricing it.
An estimator, in-house or contracted. On residential work this is the normal route. The estimator measures and prices, so the bill is rarely separated from the estimate. For a builder running 5 to 50 homes a year, this is usually one person or a part-time arrangement.
A fixed-fee take-off service. The newest route, and the one most guides ignore. These services measure only and publish a price per trade or per home, with a stated turnaround. Some now publish their fees openly and deliver a trade breakdown in a fixed number of days (Structmate). The trade-off is that you get quantities, not judgement about rates, and you own the checking. Scaleline, a DDDI Group company, works this way for new homes, with published fees and a 24 to 48 hour turnaround.
Scaleline is a DDDI Group company, and DDDI Group publishes this article. Links to Scaleline are related-party referrals, not independent recommendations. Scaleline measures new homes from drawings and does not price them; it is not an AIQS-certified quantity surveying practice.
| Route | Who pays | Measures or prices | Published price |
|---|---|---|---|
| Quantity surveyor | Client or financier | Both, or measurement only | Usually quoted |
| In-house estimator | Builder | Both | Salary |
| Fixed-fee take-off service | Builder | Measures only | Often published |
One boundary matters. Bank progress reports, cost-to-complete reports and tax depreciation schedules need a registered quantity surveyor, and a measurement service is not one. The wider QS role covers what those engagements involve, and quantity surveyor reports explains which report type needs which qualification. If you are deciding between the three routes on volume and cost, which of the three preparation routes fits your volume works through the decision by project type.
When a New Home Actually Needs One
Most detached houses in Australia are built without a bill of quantities. That is not automatically a mistake. The document earns its cost when more than one party has to price the same scope.
The strongest argument for it is duplication. The AIQS has put the case in numbers. Typically three to four builders bid on the same project, and each generates their own quantities. Roughly 25 trades each have three to four bidders. The quantity surveyor's measuring time is therefore duplicated 10 to 13 times across the market. Providing a bill to builders and trades could cut the hours required for measurement by 60 to 80 per cent (Build Australia, 15 June 2023). That is an argument about tendering efficiency, not about accuracy, and it only applies where there is a competitive tender.
Four situations change the answer for a house:
- Several builders are tendering the same job. Without a shared document, each prices a different assumed scope, and the lowest number is often the one that assumed the least.
- A client or financier wants comparability. A bill lets two quotes be read against each other line by line instead of as two totals.
- The design repeats. Townhouses, dual occupancy and anything with a repeated unit compound a quantity error across every instance.
- One document goes to every trade. A trade-formatted bill replaces a stack of separate scope descriptions with one consistent set of quantities.
The case against is simpler. A single builder pricing a single house from their own rates library already has the quantities, and paying a second party to measure them again buys nothing. An estimate will do.
Owner-builders sit in between. A bill is useful as a shopping list and a check against trade quotes. It is not a contract document. It will not resolve a dispute with a tradesperson who never agreed to it.
Priced and Unpriced Bills of Quantities
The same document exists in two states. Unpriced, it fixes scope and goes out to bidders. Priced, it carries a rate against every line and becomes the basis for valuing change.
An unpriced bill is the tender instrument. Every bidder receives identical quantities and descriptions, so the returned prices differ because of rate and judgement rather than because of assumed scope. That is the whole point of the exercise.
A priced bill does more. Each line has a rate, which means a variation can be valued against an agreed rate instead of renegotiated from the drawing. That is the function quantity surveyors describe as the primary one, and it is also the reason builders resist it. One practising quantity surveyor puts the resistance plainly. The modern builder's estimating office wants to send scope to subcontractors and let them assess it, because "they don't want to commit themselves to a rate for a variation" (Renovation Collaborative). The same interview describes a builder refusing to price a bill at all and pricing a lump sum off the drawings instead.
| Feature | Unpriced | Priced |
|---|---|---|
| Who prices it | The bidder | The measurer or the bidder |
| Protects against | Scope disagreement between bidders | Repricing every variation from scratch |
| Cost to produce | Lower | Higher |
| Becomes contractual? | Sometimes | Usually, if the contract says so |
Which one you want depends on what you are trying to control. If the risk is that two builders are pricing different jobs, you want unpriced. If the risk is that every change becomes a negotiation, you want priced. How a schedule of rates compares covers the third option, where the client carries the quantity risk instead.
The Measurement Convention: ANZSMM
Australia has a national method of measurement, and it is the Australian and New Zealand Standard Method of Measurement of Building Works: the ANZSMM, current edition 2022 (NZIQS). The first edition, ANZSMM 2018, was based on the Australian Standard Method of Measurement sixth edition and replaced New Zealand's NZS4202 (Registered Master Builders Association, 9 February 2018). Four bodies publish it: the Australian Institute of Quantity Surveyors, the New Zealand Institute of Quantity Surveyors, Master Builders Australia and the Registered Master Builders Association of New Zealand. AIQS sells it at $100 for non-members in print, or $85 digital (AIQS, checked 30 October 2026).
What it governs is description and measurement, not price. For each item it sets out what has to be stated, what unit it is measured in, and what is deducted. That is why two bills prepared to the same standard can be compared. The reader knows both deducted openings from wall areas, and both measured skirting in metres with the material stated.
Most new-home BOQs in Australia are not prepared to it. Full ANZSMM measurement is a tender instrument for work let on a measured bill. A detached house priced on a builder's own rates does not usually carry the cost of producing one. What matters in practice is that the convention is stated on the front of the bill. A reader then knows whether openings were deducted, whether wastage is included, and what was excluded.
Two other standards get mentioned in the same breath and should not be confused with it. The AIQS Australian Cost Management Manuals drive elemental cost plans, which are a planning document grouped by building element. The ANZSMM drives bills, which are a procurement document grouped by trade. A house can have a cost plan without ever having a bill. Where rates enter the process is the estimating side of that handover.
Frequently Asked Questions
What does BOQ stand for?
Bill of quantities. In Australia the same three letters are also the brand and ASX code of Bank of Queensland, which is why search results for the abbreviation alone are mostly banking rather than construction.
Who prepares a bill of quantities?
Usually a quantity surveyor on a commercial tender, an estimator on a residential job, or a fixed-fee take-off service where the builder only needs quantities. The client pays when the bill is a tender document and has to be independent of the bidders.
How much does it cost to get a bill of quantities?
It depends entirely on the pricing model: hourly, a percentage of construction cost, a fixed fee per dwelling, or a per-trade rate. What each model charges sets the published Australian prices side by side rather than quoting a single figure that would not hold.
How do you calculate a bill of quantity?
Measure from the drawings in the unit the trade prices in. Group the measurements by trade, and describe each line so someone else can price it without asking. The arithmetic is simple; the discipline is in the unit and in knowing what to deduct.
What is the difference between a BOQ and an estimate?
A bill lists measured quantities and may never carry a price. An estimate converts quantities and allowances into a forecast cost. A bill can be unpriced and still be complete; an estimate without quantities is a number with no working.
Where This Leaves the Builder
A bill of quantities is a scope document. Its value scales with the number of people who have to price the same scope. One builder, one house, own rates: an estimate will do, and a bill is an extra fee for information you already hold. Several bidders, or several trades, working off one drawing set. A shared measured list is the cheapest way to make those prices comparable. It is also the only way to value a variation against something both parties agreed to before the work started.
The preparation itself is not mysterious. Check the drawings. Fix the rules. Measure with traceability. Group by trade. Describe and unit every line. Cast and read the bill before it leaves. Then issue it with the revision it was measured from.
Scaleline, a DDDI Group company, produces measured take-offs for new homes from drawings, with a sourced line behind each quantity and a 24 to 48 hour turnaround. It measures and does not price. See a sample report to judge the output, or how it works for the process and fixed fees.
Scaleline is a DDDI Group company, and DDDI Group publishes this article. Links to Scaleline are related-party referrals, not independent recommendations. Scaleline measures new homes from drawings and does not price them; it is not an AIQS-certified quantity surveying practice.
This guide is researched and edited by the DDDI Built Environment Research desk, which publishes industry research on property development and construction in Australia. It is fact-checked against primary sources before publication, and corrections can go to the research desk through the contact page. The editorial standard behind these articles is described on DDDI's about page.