Digital Procurement & Estimating

Bill of Quantities Format: The Columns, Sections and Line Rules of a New-Home BOQ

A checkable bill of quantities format has nine columns, sections that follow the build sequence, and one rule per line: one unit, one source, and allowances flagged rather than blended in.

· DDDI Built Environment Research

Bill of Quantities Format: The Columns, Sections and Line Rules of a New-Home BOQ

A bill of quantities format is a column set and a set of line rules, not a document type. Nine columns carry every line: item code, trade section, description, quantity, unit, source sheet, measured-or-allowance, rate and amount. Get those right and someone who did not prepare the sheet can check it. Get them wrong and the totals cannot be tested.


Key Takeaways

  • Nine columns, and each answers a question someone asks later. The source sheet is the one most often dropped and the one you need at claim time.
  • Sections follow the build, not the alphabet. Trades price what they can find.
  • One unit per line. A line measured in m² cannot also carry an each item, because no rate prices both.
  • Allowances are flagged, never blended. A prime cost item is not a fixed price because a dollar figure sits beside it.
  • Excel is enough at house scale. The format is the constraint, not the tool.

The Nine Columns, and What Each One Prevents

A bill of quantities format is the column set, section order and line rules that make a measurement checkable. A measured line is one whose quantity was read from a dimensioned drawing; an allowance is one that was not. The nine columns below are the whole of it, and each one exists because of a question asked months later.

For example, the slab section below shows the pattern the other trades follow.

ColumnWhat goes in itWhat it prevents
Item codeTrade prefix plus a number: SLB-03An item that cannot be cited in a variation
Trade / sectionThe section band the line sits inScope drifting between trades
DescriptionMaterial, size, fixing, finish, heightA defensive rate priced against a vague line
QuantityThe measured figure, as a formula where possibleA typed number nobody can retrace
Unitm², m³, lm, each, item, summ² and each mixed on one line
Source sheetDrawing and revision: S4, Rev CA correct measurement of a superseded drawing
Measured or allowanceMeasured, PC item, provisional sumAn allowance read as a fixed price
RateLeft blank on an unpriced billThe measure and the price arriving as one number
AmountQuantity × rate, as a formulaA total no line supports

The source column is dropped first and regretted most. Keep the dimensions behind each quantity, not only the result: "three lengths and a height are recoverable; a lone figure of 42.75 is not" (Kestrel). The drawing reference is, in InstaBOQ's words, "the single most useful column when a quantity is queried three months later" (InstaBOQ). Revision matters as much as the sheet number: a bill measured from Revision C and tendered against Revision E is an accurate measurement of the wrong building (Structmate).


What a Sample Sheet Looks Like

Illustrative, not a real job: a single-storey home, unpriced, ex GST. The section is the band row rather than a repeated cell, and Basis is the measured-or-allowance column. Copy the structure, not the numbers.

CodeItemQtyUnitSourceBasisRateAmount
02 Slab and footings
SLB-01Concrete to slab and edge beams, N25, 100mm over 300mm24.60m³S2, Rev CMeasured
SLB-02Trench mesh to beams, laps included96.40lmS2, Rev CMeasured
SLB-03Termite barrier to slab perimeter58.20lmS2, Rev CMeasured
04 Frame
FRM-01MGP10 frame, 90mm studs at 450mm centres132.40m²S4, Rev CMeasured
FRM-02Roof trusses, supplied and erected21eachS5, Rev CMeasured
06 Roof
ROF-01Colorbond sheeting, 0.42mm, 22.5° pitch198.70m²S6, Rev DMeasured
08 Windows and doors
WIN-01Aluminium awning window, 1500 × 1200, glazed7eachS7 scheduleMeasured
10 Linings
LIN-0110mm plasterboard, walls and ceilings, set, 2.7m412.00m²S9, Rev CMeasured
SKT-01Skirting, 90 × 19 MGP10, fixed and set82.60lmS9, Rev CMeasured
11 Wet areas
WET-01Waterproofing, floors plus 150mm up walls18.40m²S9 detail 4Measured
TIL-01Floor tiling, 600 × 600 porcelain41.30m²Selections pendingPC item, $65/m²
17 Site works
EXT-01Rock excavation beyond 0.5m depth1itemNot knownProvisional sum, $6,000

Two allowance rows. Tiling has a known specification and unknown price, which is a prime cost item. Rock excavation has unknown quantity and price, which is a provisional sum. Writing either as a measured line is where budgets break.


Section Order for a New Home

Follow the order the work happens, which is the order trades are engaged:

  1. Preliminaries and site establishment
  2. Earthworks, set-out, drainage in ground
  3. Slab and footings
  4. Frame
  5. Roof and roof plumbing
  6. External walls, cladding and windows
  7. Services rough-in
  8. Insulation and linings
  9. Wet areas and waterproofing
  10. Joinery, cabinetry and fit-out
  11. Finishes, tiling and painting
  12. External works

This is a trade breakdown, not a formal elemental bill. Formal bills in Australia are measured to the Australian and New Zealand Standard Method of Measurement, published by AIQS with Master Builders Australia; ANZSMM 2022 is the second edition (AIQS; NZIQS notes). Full bills are uncommon on small residential jobs (VIABUILD), and one QS practice reports the trade breakdown as its most requested builder format (Pekaj). Estimating Australia's warning is worth carrying: "Do not assume every BOQ has been prepared to ANZSMM simply because it looks professional" (Estimating Australia). For the formal definition, see the bill of quantities guide.


The Line Rules That Make a BOQ Checkable

One unit per line. If part of the work is m² and part is each, that is two lines. Combining them forces a composite rate no trade can price.

One source per line. Sheet number and revision. A line with no source gets deleted at the first challenge, or paid without one.

Allowances flagged, never blended. A PC item or provisional sum sits in its own row with its basis stated. In Queensland a regulated contract must state allowances calculated with reasonable care and skill, with a separate schedule describing each (QBCC guidance; Domestic Building Contracts Act 2000 (Qld)). Burying an allowance inside a measured rate is how a fixed price stops being fixed.

No combined scope across trades. One trade per line, so a returned quote matches a line. "Carpentry and lockup" compares with nothing.

Descriptions carry the cost drivers. "Plasterboard to walls" leaves the pricer guessing. "10mm plasterboard, one layer, set, 2.7m ceiling" does not, and the height sits in the description because the item is measured in m².

Say whether the quantity is net or gross. Under ASMM, work is measured net as fixed in position unless stated otherwise, and waste is carried in the rate (ANZSMM, AIQS). Adding waste to both double-counts it.

Every line traceable or deleted. If you cannot point to a sheet, a detail or a stated allowance, it does not belong in a document other people will price.


Checking a Bill You Did Not Prepare

Read it in the order it was built, not from the total down. Start with the basis: drawing revisions, measurement method, assumptions. Then test three high-value quantities against the drawings, one from each of slab, frame and roof. If those reconcile, sample the rest. If any of them is out by more than a rounding margin, stop and check the revision before checking the arithmetic. The usual cause is a superseded sheet, not a sum error.


Building It in Excel Without It Falling Apart

Excel is cheap, editable and already installed. It is also where bills quietly break: "time consuming, tedious and can get confusing for large jobs" (Ulster, quoting Shen et al.).

Four habits hold it together. Make amount a formula, never a typed number. Put section headers in their own rows. Freeze the header row and code column so line 240 still has headings. Above roughly 200 lines, give each trade its own tab under a summary sheet.

A bill of quantities template gets you the columns, not the discipline, and the discipline is what survives review. If you are choosing tooling, check the free estimating software options first.


Frequently Asked Questions

What is the standard BOQ format?

There is no single mandated format for a residential bill in Australia. Formal bills are measured to ANZSMM; the practical standard is item code, description, unit, quantity, rate and amount, grouped into trade sections with allowances separated out.

What does BOQ stand for?

Bill of quantities. In Australian construction the abbreviation is unambiguous in context, though searching for it also surfaces Bank of Queensland.

Who prepares the BOQ?

A quantity surveyor for a formal tender, or an estimator or take-off service for a builder's own pricing. On small residential jobs the builder often measures and prices in one step.

What is the difference between a BOQ and a BOM?

A bill of materials lists what to buy. A bill of quantities lists measured work to be priced, including labour, which is why its units include m² and lm rather than only each and kg.

Should a residential BOQ be prepared to ANZSMM?

Not necessarily. Follow it where the bill will be tendered or used for variations. Most new-home bills are trade-grouped quantity schedules that borrow the discipline without claiming to be an ANZSMM bill.


Where This Leaves You

The format is a contract with your future self. In three months someone will ask why a slab is 24.6 cubic metres, and the sheet answers in ten seconds or costs an afternoon.

To see the format on a real drawing set, a sample bill of quantities report shows a measured sheet with source references and an accuracy class per line. Scaleline's published pricing sets out what a measured bill costs before you send a drawing.

Scaleline is a DDDI Group company, and DDDI Group publishes this article. Links to Scaleline are related-party referrals, not independent recommendations. Scaleline measures new homes from drawings and does not price them; it is not an AIQS-certified quantity surveying practice.

For the trade-by-trade version, a worked example for house construction walks each section with the units and the lines most often missed. To compare what it costs to have one prepared, what a bill of quantities costs sets out the price models.

This guide is researched and edited by the DDDI Built Environment Research desk, which publishes industry research on property development and construction in Australia. It is fact-checked against primary sources before publication, and corrections can go to the research desk through the contact page. The editorial standard behind these articles is described on DDDI's about page.

Get Trade Quotes